HomeMy WebLinkAboutRequest to Purchase - Public Works (003)Memo
Grant County
Department of Public Works
124 Enterprise St. S.E.
Ephrata, WA 98823
To: Honorable Board of County Commissioners
Grant County
From: Samuel Dart
Assistant Public Works Director
Date: January 21, 2021
Re: Authorization to Purchase Per Change Order #1
Project: Ephrata Landfill Phase 3
Authorization to purchase per attached Change Order #1:
Solid Waste:
Serial No. 2LO16
Replace the existing inoperable condensate pump at the flare facility per the attached Change Order #1
in the amount of $16,662.80, including sales tax. The total adjusted contract amount after this Change
Order #1 is $2,256,111.37.
I have reviewed the information and find it acceptable to move forward with the purchase of these
items.
Dated this ?-V day of , 2021
Board of County Co ssioners
Grant County, Washington
A r v Disapprove Abstain
Dist #1 Dist #1 Dist #1
Dist #2Dist #2 Dist #2
Dist #3W Dist #3 Dist #3
"To meet current and future needs, serving together with public and private entities, while fostering a respectful and successful
work environment."
Information ......... _......... ........ ...... _...... _(509) 7648082
Keith Eletson, County Road Engineer ......... _........ Ext 3502
Ed Lowry, SupeMeor-0bt No. L. ... ........................ Ext 3540
FAX ..... ........ ................ ..................._.........(509) 7548087
Bob Bersardl, Construction Engineer .__...
_........ »Ext. 3503
Mike DeTrollo, Supervisor -01st No. 2._ ..... _.............. Ext. 3591
E -mall_ ...... .......... .... .... publlcworksQgraMcountywa.gov
Loc Ohl, Accountant Lead._.._....._.....__.....__.....Ext 3555
John Brlssey, Supervisor0st No. 3 .................. _....... Ext. 3541
Sam Castro, Public Works Director_—..._—...ExL 3504
Rod Follett, Foreman -Sign Shop ....................... Ext. 3579
John Spiess, Supervisor -Central Shop .............(509) 7548088
Samuel Dart, Assistant Director .............. ..... .... Ext. 3519
Jason Collings, Solid Waste ............... ...... (509) 754-4319
Andy Booth, Bridge Supervisor _....... _........................ Ext. 3535
CONTRACT CHANGE ORDER
P
Parnmetriz, Inc.
Date: 1/21/2021
Project No.: 555-374(-001(05.02)
Location: Ephrata, WA
To (Contractor) KRCI, 125 SE McGee St., East Wenatchee, WA 98802
Contract No.: Ephrata Landfill PH3
Development
Change Order No.: 0l
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item
No.
Description of changes — quantities, units, unit prices, change in
completion schedule etc.
Increase in
Contract Price
Decrease in
Contract Price
1
Replace the existing inoperable condensate pump at the Flare
Facility.
Sub -Total — Increase
Sub -Total — Decrease
8.r/9 Tax
Total increase
Net increase Contract Price
$15,400.00
$15,400.00
$
$ 1,262.80
$
$16,662.80
$
$16,662.80
$
The sum of $ 16,662.80 is hereby added to the total contract price, and the total adjusted contract price to date thereby is
$ 2.256.111.37.
The time provided for completion in the contract is (unchanged) (increased) (decreased) by 2 work days. This document
shall become an amendment and all provisions of the contract will apply hereto.
R.eoommen by
En ' eer. Steve Em P.E.
Date: 01/21/2020
Ac=pWby
Contractor:
Date: 1/.Z11-02-1
Approved by
Owner:
Date:
FORM 9"(7,0)
Ephrata Landfill Phase 3
KRCI, LLC Condensate Pump Replacement
1/20/2021
Devon Gray
ESTIMATE NOTES
Includes mobilization, removing water from manhole, replacing pump, refilling
manhole, startup, and installation troubleshooting. Assumes use of landfill water
truck for condensate. Assumes pumped out condensate will be used to refill
manhole or landfill will provide additional/alternative water.
Includes Meyers Pump (see attached cut sheet), cast iron elbow with flange and
guide plate that will retrofit existing skids, and replacement pull chain. Price for 2
pumps per each provided as requested.
Electrical work to be done by Stetner Electric.
Unit of Extended
Item
Description
Quantity
Measurement Unit Price Price Note
I
Pump Replacement Labor
I
LS $4,100.00 $4,100.00 A
2
Pump Replacement Materials
2
EA $3,900.00 $7,800.00 B
3
Pump Replacement Electrical
1
LS $3,500.00 $3,500.00 C
TOTAL $15,400.00
ESTIMATE NOTES
Includes mobilization, removing water from manhole, replacing pump, refilling
manhole, startup, and installation troubleshooting. Assumes use of landfill water
truck for condensate. Assumes pumped out condensate will be used to refill
manhole or landfill will provide additional/alternative water.
Includes Meyers Pump (see attached cut sheet), cast iron elbow with flange and
guide plate that will retrofit existing skids, and replacement pull chain. Price for 2
pumps per each provided as requested.
Electrical work to be done by Stetner Electric.